CLAUSE CODE: QC15-N    This clause was archived as of 04/24/2012
  CLAUSE TITLE: Critical Process Certification


QC15-N CRITICAL PROCESSES CERTIFICATE [NASA AQC12]:

 

The following shall apply to JPL designated “critical processes” performed by Contractor:

Contractor shall notify JPL of proposed changes in process definition and, shall obtain approval from JPL prior to implementing the change. Changes affecting processes, production equipment, tools, and programs shall be documented. Procedures shall be available to control their implementation.

The following shall apply to Contractor designated “critical processes” that have been subcontracted:

The Sub-tier Supplier shall notify Contractor of proposed changes in process definition and, shall obtain approval from JPL prior to implementing the change. Changes affecting processes, production equipment, tools, and programs shall be documented. Procedures shall be available to control their implementation.