CLAUSE CODE: QC22b    This clause is current as of 04/19/2024; 12:47:11
  CLAUSE TITLE: Objective Evidence of Dimensional Inspection


QC22b - Objective Evidence of Dimensional Inspection:

Subcontractor shall provide objective evidence with each shipment that the first article in the Subcontract/Purchase Order (PO) was dimensionally inspected for conformance with drawing and Subcontract/PO requirements. Objective evidence shall consist of records of actual dimensional readings taken during inspections of each part, with the dimension and its tolerance noted.

All out of tolerance measurements shall be clearly identified on the inspection records and the disposition of that part noted by Subcontractor’s authorized Quality Assurance department. This information shall be submitted to JPL for acceptance/rejection of the out-of-tolerance condition prior to hardware delivery.

Subcontractor shall identify each inspection record to the related Subcontract/PO, part number, revision, and when applicable, serial number. The authorized management representative responsible for the Subcontractor’s inspection activity shall certify with signer’s title and date of signature that all of the shipped parts were indeed inspected to the criteria specified and those actual measurements are the ones provided. If serial numbers are not assigned, then the Subcontractor shall devise a method of linking the record of dimensional measurements with the specific part measured (i.e., taped, bagged together, etc.).

Inspection equipment (i.e., tools and gauges) used during dimensional measurement shall have its identification numbering recorded and allow the ability to recall the parts inspected with that particular inspection device in the event it is subsequently found to be significantly out of tolerance.