JPL Test Witnessing is required
for all of the following: acceptance tests, qualification tests, environmental
tests, and nondestructive tests performed on items delivered under this
Contract/Purchase Order. Other tests requiring a JPL witness may be listed in a
Statement of Work accompanying the Contract/Purchase Order.
JPL source test verification is required for first article final electrical
(Functional Test) and other times as required in the Contract/Purchase Order,
prior to the shipment of articles from the Contractor’s facility.
Contractor shall promptly notify the JPL Procurement Quality Assurance (PQA)
office at http://eis.jpl.nasa.gov/qa/PQA/servicerequest.cfm
so the appropriate inspection can be coordinated. The following phone number
may be accessed if necessary: (818) 393-7593.
Test witness source inspection
shall be conducted by JPL at Contractor’s facility, or other location where
designated in the Contract/Purchase Order. Contractor shall make available to
the JPL QA Representative all applicable Contracts/Purchase Orders, drawings,
specifications and changes thereto, related test procedures, inspection and/or
test equipment, and such other information, personnel, and resources as may be
required to satisfactorily perform the inspections and tests required under
this Contract/Purchase Order. Contractor shall ensure the current calibration
and required accuracy of all instruments provided to the JPL QA representative
accomplishing the test witness source inspection. Contractor shall provide a
suitable workspace and environment to conduct the source inspection.
Locale
|
Business days advance notice
|
Notes
|
Local:
In-state
|
3
days
|
Minimum
required
|
National:
Domestic
|
5
days
|
Minimum
required
|
International
|
10
days
|
Long
lead time/forecasting desired
|